  In order to ensure the progress of the project, the G330 Tongling Section of the first-class highway reconstruction project (Phase I) strictly grasped the epidemic prevention and control, vigorously protected the progress of relocation, and worked overtime to promote the project construction。

  First, we will strictly enforce epidemic prevention and ensure safety。According to the requirements of the local government, the G330 project Office has adopted closed management measures for all participating units. All personnel take temperature measurement and nucleic acid detection at the construction site and the resident every day, and carry out nucleic acid sampling three times a week. No personnel is allowed to go out。Offices, public toilets, kitchens and other parts of the daily disinfection, outside visitors without appointment do not meet, simultaneous temperature measurement and two-yard joint inspection work, cafeteria dining to implement the peak system, strict and meticulous epidemic prevention and control measures。

  Second, we will strengthen docking to promote levy and demolition。The first phase of G330 Tongling Section I Highway reconstruction project involves two sections in Zongyang County and suburban areas, and the project expropriation and demolition work has been vigorously promoted。Up to now, Zongyang County has signed a demolition agreement for 149 households, the suburban section of the social stability assessment has been approved, waiting for the announcement of the demolition, resettlement announcement immediately start the demolition agreement work。At the same time of signing the relocation agreement, the G330 project Office, together with the Zongyang County demolition headquarters and the heads of relevant townships, actively docking and coordination on the spot, communicating and understanding the situation of the demolition and difficulties encountered in the process, and solving them in a timely manner。At present, the demolition work of 11 households has been completed。At the same time, pay great attention to the dynamics of suburban expropriation and demolition work, and ask the Municipal Transportation Bureau to take the lead in solving the project involving the balance of arable land and the implementation of related funds。

  Third, work overtime to ensure progress。Under the big goal of completing 50% of the subgrade construction of the project this year, the participating units actively cooperate, work overtime under the premise of quality, quantity and civilization construction, "dry on sunny days, find a way to dry on rainy days", and vigorously promote the physical construction of the project。In the project construction at the same time, the work of production safety is also unremitting, through the on-site inspection, the form of holding a safety meeting requires the construction personnel to improve awareness, pay attention to safety work。Up to now, 37,300 ㎡ of original surface clearing has been completed, 167,000 m³ of earthwork excavation, and 10,000 m³ of excavation unless applicable materials (excluding silt, rock salt and frozen soil) have been completed. There are more than 40 construction machinery on site, and all working faces have been working overtime to vigorously promote and ensure the completion of the annual target tasks。